A77 Resurfacing Between Sandyford Toll & Dutch House Roundabout

Scotland Transerv have provided an update on their proposed overnight closures of the A77 during resurfacing works later this month.  For those heading north from Sandyford Toll to Dutch House roundabouts, there will be seven consecutive 8pm to 6am closures from Friday 14th to Thursday 20th September

------

Scotland TranServ:

Following feedback from key local stakeholders Scotland TranServ have amended their delivery plan to carry out resurfacing on a 3.5km stretch of the A77 northbound carriageway between the Sandyford Toll and Dutch House Roundabouts.
 
In order to complete this £300,000 programme of works, it will be necessary to implement a series of seven overnight closures starting from 8pm on Friday 14th September.

Working with local stakeholders

Scotland TranServ has responded to concerns of key local stakeholders and rescheduled the original programme of works from a full weekend closure to a series of overnight closures. Our works have been co-ordinated to ensure that the traffic impact on the A77 and the diversion route have been timetabled to avoid works on the diversion route and minimise disruption for local commuters and businesses.
 
We will resurface approximately 12,500m2 of the A77 northbound trunk road. This is an important project for Scotland TranServ, and having been postponed in August, it was important for us to complete the works as soon as possible and in advance of the winter period. The window in our resurfacing programme will now allow us complete these works.

Hours of working

Works will be carried out under full OVERNIGHT closure of the A77 northbound during the following times: 

  • 8pm Friday 14th to 6am Saturday 15th September
  • 8pm Saturday 15th to 6am Sunday 16th September
  • 8pm Sunday 16th to 6am Monday 17th September
  • 8pm Monday 17th to 6am Tuesday 18th September
  • 8pm Tuesday 18th to 6am Wednesday 19th September
  • 8pm Wednesday 19th to 6am Thursday 20th September
  • 8pm Thursday 20th to 6am Friday 21st September

In order to allow the carriageway to cool and harden sufficiently it will be necessary to implement a lane 1 closure on Sunday 16th September.

Local diversions

Local diversions will be in place during these overnight closures. All A77 northbound traffic during this period will be diverted at Whitletts Roundabout via Heathfield Road, Ayr Road, Prestwick Main St, Monkton Road, A79 to Monktonhead Roundabout, A78 to Dutchhouse Roundabout.  For further details on the diversion route, please click on the link below.
 
A77 southbound traffic will NOT be affected. Local access will be permitted as far as Sandyford Toll Roundabout and Emergency Services will be permitted through the works at all times.
 
Drivers are asked to allow additional time for their journeys. For live trunk road updates please follow @trafficscotland on Twitter or visit trafficscotland.org.

CLICK HERE TO VIEW DETAILED DIVERSION MAP